Ted Berry Company, Inc.
Municipal & Industrial Cleaning ~ Video Pipeline Inspections
24 HOUR EMERGENCY SERVICE

521 Federal Road, Livermore, Maine 04253
Office: 207-897-3348
Fax: 207-897-3627
24 Hour Emergency Pager: 207-758-8306

WHAT'S NEW

  
 


Municipal Services Team

Smoke Testing of the North Jay, Maine sanitary sewer collection system. June 2008


Matt, Alfred, Mark, Eric, Shawn and Garrett

Trenchless Technologies Team


 May 20th, 2008

Aqua-Maine needed a new solution to replacing existing small diamater water mains in it's Rockland and Owl's Head water system. On tuesday May 20th along with the Aqua-Maine team over 700' of 2" - 2 1/4" Cast Iron cement lined water main was replaced utilizing the static pipebursting method. The Ted Berry Team used our Hammerhead HB5058 adapted with 35mm rod and a ductile iron slitter. New product pipe was HDPE SDR 9 CTS with a tracer wire. Project Engineer Steve Cox. Ted Berry Project Manager Matt Timberlake.



Pulling 2" HDPE - SDR 9 CTS


The Aqua-Maine crew at the launch pit..
_________________________________________

Industrial Pumping Team


Monday May 12th, 2008

The Ted Berry Industrial Pumping Team was called on to pump out (2) 4.5 million gallon aeration lagoons at the New Page Rumford Mill. Project Manager Jack Berry utilized our 6"-8"-12" trash pumps, 6"-8" sludge pumps with HDPE suction and discharge tubes, 15,000 PSI hydroblaster, industrial vacuum truck, and other support equipment.. Project called for the lagoon to be emptied, washed, and new HDPE aeration tubes fabricated and installed. Total project completed in 4 days, meeting the critical deadline for the mill!!!


Chuck, Sean, Ben, Jack, Mike B., Mike G. - "Get 'er Done Boys!"


Shawn, Chuck, Garrett, and Eric fusing HDPE pipe aerators. 5/14/2008


BIG PUMPS - 20,000 gpm total. (2) 12" trash, (1) 8" trash, (1) 6" trash, (1) 6" hydraulic, (1) 8" hydraulic

___________________________________________________________________________________________________________

Trenchless Technologies Team

Thursday May 8th, 2008

The Ted Berry Company Trenchless Technologies Team completed a static pipeburst for McGee Construction of Gardiner, Maine. The project consisted of replacing an existing 6" VCP gravity sewer main with new 6" HDPE in Norway, Maine. The service line would serve a new Walgreen's store and ran under the entrance to Tim Horton's Coffee. Disruption of service for Tim Horton's was not an option. Site Superintendent Seth McGee oversaw the operation which included an inspection by the Norway Sewer department Superintendent Shawn Brown. The Ted Berry Company utilized our Hammerhead HB5058 static rod burst machine with a bladed starter rod and expander head. The entire 120' section of pipe was replaced in approximately one hour. Total time on site was 5 hours start to finish. Ted Berry Team consisted of Shawn Ready, Kris Jerry, Garrett Lovewell, and Eric Gemelli.


The launch pit. Into existing brick manhole.

____________________________________________________________________________________________________________

From April issue of Trenchless Technologies Magazine
Randy Happel — Apr 01, 2008

Driving into the picturesque New England village of Northport, Maine, for the first time along its narrow, winding streets is likened to entering a storybook setting. Meticulously landscaped yards surround decoratively painted cottages — blue, yellow and pink in color and clad with ornate trim work — many of which are individually named and identified by rustic, hand-painted signs.

Located on Maine’s rugged eastern coast and home to approximately 1,500 residents, Northport is a resort community comprised mostly of seasonal dwellers. The place is so remote that the majority of Maine’s 1.4 million residents have never heard of it.

Those who make Northport their year-round residence go to great lengths to maintain the quaint integrity of this historic community, which has roots that date back to the early 1600s with the arrival of a contingent of French explorers. So it’s not surprising that when Matt Timberlake and crew arrived in town to tackle an intricate sewer line rehab project, the locals took interest.

“You have to understand the dynamics of the community to fully understand this project,” Timberlake says. “I don’t remember a time in the history of our company when a condition for accepting our proposal included a provision to educate affected residents about the process of how we would complete the project so homeowners understood exactly what was going on. The whole community got involved.”

Timberlake is vice president of the family-owned and operated Ted Berry Co., headquartered in nearby Livermore, Maine. Ted Berry Co. has been in business for more than 35 years and specializes in offering diverse methods of completing infrastructure installation and rehab projects. Timberlake had worked with the Northport Village Corp. since 2005, when Ted Berry Co. was contracted to implement an ongoing inspection of the town’s sewer system. During one of their routine inspections, Timberlake’s crew discovered a section of pipe that had become infiltrated by root growth.

Location, Location, Location

According to Timberlake, the project was a textbook case for a pipe burst. The affected sewer line originated from a residential street at its upper end, continued under four private residences, wound between two other homes and ended at a manhole located within 25 ft of the high tide mark of the Atlantic Ocean. Although the sewer discharge line was only about 200 ft in length, the beginning and ending manholes were not within view of each other. Excavation was a concern at the downstream end, given its proximity to the ocean and the highly visible Northport Yacht Club. 

“Many things told us this was not an excavation job,” Timberlake says. “There were established trees and shrubs, walkways, lawns, patios and decorations to contend with. Had we plowed a trench, we would have had to dig right alongside the foundation of a couple of these homes. The long-term effects that disturbing a foundation may cause brought a whole other set of potential issues. Trenching was just not an option.”

Timberlake and trenchless technology supervisor Shawn Ready rolled up their sleeves over dinner one night and got to work on a proposal. Both had been on the inspection team that discovered the root infiltration problem, so the two men were intimately familiar with the layout. They quickly came to a consensus on the best rehab method, but the details of the plan took a bit more time and included stipulations that were somewhat unconventional compared to proposals the two had drawn up in the past.

“Although the village corporation had a legal easement to go through individual properties in order to maintain the sewer line, their first concern was how repairing it would affect the residents,” Timberlake says. “Explaining how we would complete the project to the affected homeowners and getting their buy-in made it an easy sell to the council slated to approve the job.”

The plan Timberlake and Ready proposed included going door-to-door with a representative of the village corporation to explain to residents exactly what needed to happen and how it would be accomplished. By doing so, Timberlake and his crew immediately won over the locals.

In order to preserve the downstream manhole near the shoreline and eliminate the need to employ excavation, the plan Timberlake and Ready devised called for pneumatic pipe bursting. Although the company had completed 40 to 50 static bursts in the past, this would be the first pneumatic burst for Ready and his crew. Therefore, Ready consulted with Brian Cowles, Ted Berry’s HammerHead rep, for guidance during the pre-planning phase and to ensure his crew was well-versed in the project’s details before getting started.

“We had traveled with Hammerhead to several pneumatic jobsites over the previous couple of years, so we were very familiar with the process,” Timberlake says. “It wasn’t really anything all that new. Some of the details of the pneumatic hammer, however, were things that internally we spent a great deal of time planning in advance. And HammerHead was a tremendous help.”

Timberlake went on to explain that the project would have been very easy to complete using static equipment, but he didn’t want to take any chances removing the downhill manhole or digging that close to the shoreline.

“Protecting the integrity of the site was important to us,” Timberlake says. “Nobody from the village corporation actually told us we had to do it a certain way. But we knew the smaller footprint we left meant they would be more apt to have us back. Plus, that’s just how we do business.”

After many hours of planning followed by a day of preparation, the burst commenced at 9 a.m. on a November morning. Ready and his crew had positioned a HammerHead HG12, a 12-ton winch, on the lower end with an 8-in. hammer and a 10-in. burst head at the topside. Using the “Manhole Exit Method,” a process patented by HammerHead that eliminates one excavation at the manhole, decreased the amount of excavation necessary by 50 percent. By lunchtime, the burst had been completed and the new pipe was in place. By early afternoon, backfilling was complete and services were restored.

“The job was completed in under four hours,” Timberlake says, “witnessed by what we affectionately called the ‘advisory committee’ … made up of local residents. One of the homeowners was present when we dug the topside launch pit on his property. He had approximately 60 plastic pink flamingos randomly situated on the site. I have pictures of Shawn [Ready] repositioning each flamingo back to its original spot from the map we had created prior to initiating the burst. Most were facing east, but there were a few that faced west. We made sure that we replaced each of them in their original spots and facing the same direction.”      

Tips for Other Contractors

While proud of the work his crew performed on the Northport project, Timberlake viewed the process as just another example of how Ted Berry Co. approaches every job. And while a pneumatic burst was uncharted territory for his company, Timberlake has some valuable advice for other contractors.

“Don’t be too proud to ask for help,” he says. “Contractors are typically bad at that. We’ve been in business long enough that we know we don’t know everything. But we have connections to people who have the know-how when we are in need of technical support. Like our relationship with HammerHead, for example, they were onsite from start to finish assisting with completing our company’s first pneumatic burst.”  
Timberlake is also a firm believer in involving all interested parties in the project — not only his own crew, but the supervisors, project managers and the affected residents.

“Educate the public,” Timberlake says. “A lot of times we show up on these jobsites and the public is standing there looking at us like, ‘What the heck are you guys doing here?’ We make it a point to go out of our way to knock on doors and let people know what we are up to. I think contractors as a whole need to get better at that.”

A Job Well Done

Aside from all the planning, calculations and gratification of a job well done, it’s the approval of local residents that means the most to Timberlake.

“I understand their anxiety,” he says. “I know how I would feel if a bunch of guys in vests and hard hats were to invade my property with all this equipment and not knowing what was going to happen. We never lose sight of that. I guess the biggest compliment to come from the Northport job was when the guy who was there when we first started the burst later renamed his home ‘Sewer View Cottage.’ We laughed about it at the time, but afterward, it really sunk in just how monumental that was.”

Randy Happel is a technical writer, based in Des Moines, Iowa.

New year, same problem with treatment plant

,
Wednesday, April 23, 2008

FARMINGTON - Selectmen on Tuesday reviewed a plan to improve the flow of treated water leaving the wastewater treatment plant.

Officials are contending with heavy silt that travels down the Sandy River and covers diffusers - pipes extending from the plant into the river. By blocking the diffusers, the silt prevents the treated water from properly leaving the plant.

Officials, in collaboration with the state Department of Environmental Protection, have a plan to remove the sand and silt, extend the diffusers, and set them at either a 45- or 90-degree angle. Engineer Michael Stein with the Portland engineering firm of Woodard & Curran explained the proposal to selectmen Tuesday.

A quote from the Ted Berry Co. of Livermore for a total of $26,000 to complete the work was included in the plan. Costs include a dive team, a construction crew, materials to extend the diffusers, and riprap to protect the diffusers, Stein told the board.

A sum of $18,241 was left over from a previous treatment plant project and could be used, Town Manager Richard Davis said. Possible funding from DEP will be explored for the remaining portion needed.

Whether the sand dredged from the river will be available for the town to use will be addressed, Stein said. DEP wants to look at it first to see if it's hazardous. If they find it unacceptable, the town will also be responsible for the cost of removal, he said.

The discharge system was installed two years ago when the state required the town to change the previous discharge location, Superintendent Steven Moore has said.

Earlier this year, the discharge pipe was not working properly, backing up into the plant. After the pipe was flushed in January, the problem appeared to be solved. Then in March, the same problem occurred again, he said. Divers found several feet of sand covering the outflow pipe, he said.

While there is no guarantee that the new plan will solve the problem, Selectman Dennis Pike asked Stein how certain he is that this is the answer.

Stein referred to an update in the plan that suggested three additional items be added, including a field test on the depth of sand that has only been estimated; a geologist review of part of the Sandy River by University of Maine geologist Tom Eastler; and a better estimate of the size and slope for the riprap suggested to protect the diffusers.

"A total of $340,000 was spent on the (previous) project that didn't work and now another $26,000 is needed with no guarantees it will work, how long does the town have to continue to be responsible?" Selectman Nancy Porter asked.

Seeing no alternative, the board agreed to continue on the course of action recommended since the sand has not naturally flushed itself from the site as the board had previously hoped.

Upcoming Trade Shows and Training Sessions

Northeast Trenchless Association - Summer Outing
Saturday August 9th, 2008 Monmouth, Maine

APWA - Highway Congress Skowhegan, Maine June 5th
AGC-Maine Dozer Days - Saturday June 28, 2008 10:00am-3:00pm



Northeast Trenchless Association
2008 Annual Meeting
January 14th-15th, 2008
@Framingham, MA




2008 NTA Board of Directors
Brian Dorwart, Matt Timberlake, Ralph Edwards, Danielle Martin, Bruce Hubbard, James Hargraves

OGUNQUIT — Residents on Stearns Road may have noticed some increased activity recently. That's because the Ogunquit Sewer District is getting ready to replace an aged sewer main there. What's interesting about the project, though, is the technology the district will use to replace the old pipe. It's called pipe-bursting and the process minimizes the need to dig up the road there to lay the new pipe.

"We're upgrading an old cast iron forced main that was placed there in 1962 or '63," said Phil Pickering, the district's Superintendent. "It's 1,600 feet. We'll upgrade the 4-inch cast iron pipe to a 6-inch high density polyethylene pipe. We'll use a pipe-bursting method, the same as we successfully used on the River Road project."

Put simply, pipe-bursting is a method in which an existing pipe is fractured and displaced while a new one is drawn in to replace it.

"We'll dig pits that are 400 feet apart," Pickering said. "We use a hydraulic hammerhead. We insert steel rods to pull the new pipe through and burst the old pipe. The rods have a cutting head that scores the old pipe. Then a bull head pushes the old pipe aside. It pulls a 400-foot length of the new pipe into the hole."

The U.S. Army Corps of Engineers' Guidelines for Pipe Bursting offers a detailed description of the method: "Typical pipe-bursting involves the insertion of a conically shaped tool (bursting head) into the old pipe," according to the Guidelines. "The head fractures the old pipe and forces its fragments into the surrounding soil. At the same time, a new pipe is pulled or pushed in behind the bursting head. The base of the bursting head is larger than the inside diameter of the old pipe to cause the fracturing and slightly larger than the outside diameter of the new pipe, to reduce friction on the new pipe and to provide space for maneuvering the pipe."

Pickering explained that the 400-foot lengths of pipe will consist of 10, 40-foot lengths that are fused together. "The pipe is all fused together, so there are no weak points," he said.

With the exception of the pits that will be dug, excavation is minimal. "It saves time, materials, and tearing up the road," said Pickering. "It's very cost-effective."

The cost of the project is $90,000, Pickering said. The Sewer District, as is often its custom, will serve as general contractor on the project overseeing the work being done. "We got price estimates from two contractors," Pickering said. "A third contractor we approached never submitted anything. [The winning bidder] is the Ted Barry Company of Livermore."

The project will start at the lighthouse and work its way up Stearns Road. Pickering estimated that the entire project would take five days, with another week or so for cleaning things up. "There will also be some minor excavation around the corners," he said.

The upgrade should eliminate the need for further upgrades for quite some time, given the quality of the new plastic pipe. "It has an estimated 100-year lifespan," Pickering said. "But it could be closer to 500 years. It's the type of material that nothing affects."




Maine Wastewater Control Association
Golf Tournament @ Sunday River, Maine

Jim, Matt, Shawn, Andy, & Kevin
September 19th, 2007
GO TEAM RED!

Mark Holt (Jay Sewer Department)and Kent Mitchell (Livermore Falls Sewer Department)hard at work @MWWCA


 
 
 

[Home] [About Us] [Industrial] [Municipal] [Links] [Projects] [What's New]

 

Web Design & Hosting by:
HostingHere.com